Main Road Bridge Update #17 - May 11, 2018

[Project Update]

Friday, May 4, 2018: The survey data download is complete, and is being implemented into equipment. Crews are setting survey markers for final grading.

Monday, May 7, 2018: Roper Construction began working the existing millings to bring up the moisture content for rolling for compaction.  They also started bringing in additional base course from Ruidoso Sand and Gravel.

Tuesday, May 8, 2018: The contractor continued to bring in base course material and preparing the site for final grading.

Wednesday, May 9, 2018:  Contractor brought in final 100 tons of base course and is doing final grading on the roadway. The Village of Ruidoso and the contractor discussed signage, striping, and final seeding of the site.

Thursday, May 10, 2018: Roper Construction has finished grading the roadway and has shot prime oil for paving tomorrow.

Anticipated progress for next week is as follows:

·      Job site cleanup

·      Installation of guardrail

·      Striping of roadway

·      Installation of road signs

·      Hydro-mulching of disturbed area

If you have any questions on the project, please contact Village Hall at 575-258-4343