Ribbon Cutting for the Main Road Bridge
Join us for a ribbon cutting for the Main Road Bridge in the Upper Canyon on Wednesday, June 13th at 3:00 PM. Village officials will be on-hand to celebrate a successful project that was completed on-time and under budget.
Main Road Bridge Update #18: May 19, 2108
The Main Road Bridge in the Upper Canyon has officially re-opened! Crews finished the project yesterday afternoon and traffic is now flowing across the bridge.
Main Road Bridge Update #17 - May 11, 2018
Friday, May 4, 2018: The survey data download is complete, and is being implemented into equipment. Crews are setting survey markers for final grading.
Main Road Bridge Update #16 - May 4, 2018
Friday, April 27, 2018: Roper Construction began cleaning up the site and started backfilling the Gabion Baskets with top soil. Kimo Construction finished the construction of Gabion Baskets and is preparing to de-mobilize.
Main Road Bridge Update #15 - April 27, 2018
Friday, April 20, 2018: Roper Construction continued to level out the bottom of the river on the east side of the river and has backfilled the sewer line. Kimo Construction completed the third row of baskets on the southwest side (upstream) and has started on the Gabion Basket install on the southwest side closest to the bridge (downstream).
Main Road Bridge Update - April 20, 2018
Friday, April 13, 2018: Roper Construction excavated part of the footings on the southwest side of the river and prepared it for Gabion Basket installation. Kimo Construction completed work on the southeast side of the river and began installation of the Gabion Baskets on the southwest side of the project.
Main Road Bridge Update #13 - April 13, 2018
Friday, April 6, 2018: Roper Construction completed the footings and bedding on the southeast side of the river, and Kimo Construction began placement of the baskets on the southeast side of the river.
Main Road Bridge Update #12 - April 6, 2018
Friday, March 30, 2018: GOOD FRIDAY.
Monday, April 2, 2018: Roper Construction brought in a second excavator with a Teledyne to break up large boulders that have been encountered on the southeast footings for the Gabion baskets. Kimo Construction continued to work on the construction of the northwest Gabion Baskets.
Main Road Bridge Update #11 - March 30, 2018
Friday, March 23, 2018: Roper Construction assisted Zia Engineering in shooting the Gabion grade and confirmed elevations on the northwest bank of the river. Kimo Construction continues to work on Gabion Baskets on the northeast river bank.
Main Road Bridge Update #10 - March 23, 2018
Friday, March 16, 2018: Roper Construction grouted bridge footings, and began removing overburden from under and around the bridge
Main Road Bridge Update #9 - March 16, 2018
Friday, March 9, 2018: We received word from Terracon Testing labs that the 3-day concrete test passed, and we also received confirmation from Zia Engineering which allows crews to get back to work.
Main Road Bridge Update #8 - March 9, 2018
Friday, March 2, 2018: The contractor continued to keep footings pumped out, and construction of the forms has begun. Crew members are beginning the building of rebar baskets.
Main Road Bridge Update #7 - March 2, 2018
Friday, February 23, 2018: There was still extremely heavy river flow with the river running at 22.2 CFS (9,964 GPM).
Monday, February 26, 2018: The river flow was finally down to 9.36 CFS (4,575 GPM), and Roper Construction was able to begin cleanup at the site and reinstalled the HDPE bypass pipe.
Main Road Bridge Update #6 - February 23, 2018
Friday, February 16, 2018: Heavy rains event prevented work as the river running at 80 CFS in the morning (35,907 GPM), and by the afternoon it was up to 200 CFS (89,767 GPM).
Main Road Bridge Replacement Update #5 - February 16, 2018
Friday, February 9, 2018: Roper Construction continued to haul off overburden to the Grindstone site to run through the grizzly and separate rock. The contractor is bringing a small excavator with Teledyne to complete rock removal at the north headwall, and George Esqueda from Zia Engineering was on-site doing inspections.
Main Road Bridge Replacement #4 - February 9, 2018
Friday, February 2, 2018: It was determined that a gas line was in the way of the footings for headwalls, and Zia Natural Gas Company was contacted. They made the decision that the line could be relocated, and in an effort to expedite the process, Roper Construction would do the digging, and then Zia Gas would move the gas line on Tuesday 2-6-18.
Main Road Bridge Replacement #3 - February 2, 2018
Crews completed the removal of both head walls and continued hauling off waste material as efforts continued to break-up larger pieces of concrete around the structure.
Main Road Bridge Construction Update #2 - January 26, 2018
Roper Construction began work on the Main Road Bridge on Monday, January 22, 2018, with the actual road closure occurring at 8:00 AM. The detour route began evolving with citizen and business owner input as the Village met with the NMDOT to take suggestions for the detour route.
Main Road Bridge Construction Update #1 - January 19, 2018
Construction on the Main Road Bridge in the Upper Canyon is set to begin on Monday, January 22. Crews from Roper Construction will be working Monday - Friday from 7:00 AM - 5:30 PM for approximately 120 days to complete the project. These times can vary due to inclement weather and longer days.
Main Road Bridge Construction Coming - January 2018
The Main Road Bridge Project is set to kick-off in January 2018. There will be a lot of information coming out over the next few weeks about construction schedules, detour routes, and how to navigate the Upper Canyon during the project. Keep checking this page for updates.