Main Road Bridge Update #15 - April 27, 2018

Friday, April 20, 2018: Roper Construction continued to level out the bottom of the river on the east side of the river and has backfilled the sewer line. Kimo Construction completed the third row of baskets on the southwest side (upstream) and has started on the Gabion Basket install on the southwest side closest to the bridge (downstream). 

Read More
Announcement, PSA Kerry Gladden Announcement, PSA Kerry Gladden

Main Road Bridge Update - April 20, 2018

Friday, April 13, 2018: Roper Construction excavated part of the footings on the southwest side of the river and prepared it for Gabion Basket installation. Kimo Construction completed work on the southeast side of the river and began installation of the Gabion Baskets on the southwest side of the project. 

Read More
Announcement, PSA Kerry Gladden Announcement, PSA Kerry Gladden

Main Road Bridge Update #12 - April 6, 2018

Friday, March 30, 2018:  GOOD FRIDAY.

Monday, April 2, 2018:  Roper Construction brought in a second excavator with a Teledyne to break up large boulders that have been encountered on the southeast footings for the Gabion baskets.  Kimo Construction continued to work on the construction of the northwest Gabion Baskets.

Read More
PSA, Announcement Kerry Gladden PSA, Announcement Kerry Gladden

Main Road Bridge Update #7 - March 2, 2018

Friday, February 23, 2018: There was still extremely heavy river flow with the river running at 22.2 CFS (9,964 GPM).

Monday, February 26, 2018: The river flow was finally down to 9.36 CFS (4,575 GPM), and Roper Construction was able to begin cleanup at the site and reinstalled the HDPE bypass pipe.

Read More
Announcement, PSA Kerry Gladden Announcement, PSA Kerry Gladden

Main Road Bridge Replacement #4 - February 9, 2018

Friday, February 2, 2018: It was determined that a gas line was in the way of the footings for headwalls, and Zia Natural Gas Company was contacted.  They made the decision that the line could be relocated, and in an effort to expedite the process, Roper Construction would do the digging, and then Zia Gas would move the gas line on Tuesday 2-6-18.

Read More