Main Road Bridge Update #13 - April 13, 2018

4-13-18

[Project Update]

Friday, April 6, 2018: Roper Construction completed the footings and bedding on the southeast side of the river, and Kimo Construction began placement of the baskets on the southeast side of the river.

Monday, April 9, 2018:  Roper Construction began back-filling areas around the wing walls as Kimo Construction continued working on the southeast Gabion Basket installation.

Tuesday, April 10, 2018: Roper Construction began digging on the southwest side of the river.  Roper Construction exposed all the utilities and drainage at the southwest wing wall and began digging on the southwest footings.  Kimo Construction continued working on the southeast Gabion Baskets.

Wednesday, April 11, 2018:  Roper Construction continues working on the southwest footings.  Roper Construction encountered a sewer line on the southwest side of the river that appears to be very close to the Gabion Basket installation. Kimo Construction continues work on the southeast side of the river and has prepared baskets for the southwest side of the project.

Thursday, April 12, 2018: Roper Construction assisted Village crews in securing a sewer line located on the southwest side of the project. Roper Construction has begun preparing the first part of the footings on the southwest side. Kimo Construction continues work on the southeast Gabion Baskets.

Anticipated progress for next week is as follows: 

·      Roper Construction to complete footings on the southwest side of the river. 

·      Kimo Construction to complete southeast Gabion Baskets and begin installation of baskets on the southwest side of the project.

 If you have any questions on the project, please contact Village Hall at 575-258-4343

Previous
Previous

Ruidoso Moves to Level II Fire Restrictions

Next
Next

Lane Closures for Sewer Line Maintenance