Main Road Bridge Update #16 - May 4, 2018
Friday, April 27, 2018: Roper Construction began cleaning up the site and started backfilling the Gabion Baskets with top soil. Kimo Construction finished the construction of Gabion Baskets and is preparing to de-mobilize.
Main Road Bridge Update #13 - April 13, 2018
Friday, April 6, 2018: Roper Construction completed the footings and bedding on the southeast side of the river, and Kimo Construction began placement of the baskets on the southeast side of the river.
Main Road Bridge Update #12 - April 6, 2018
Friday, March 30, 2018: GOOD FRIDAY.
Monday, April 2, 2018: Roper Construction brought in a second excavator with a Teledyne to break up large boulders that have been encountered on the southeast footings for the Gabion baskets. Kimo Construction continued to work on the construction of the northwest Gabion Baskets.
Main Road Bridge Update #6 - February 23, 2018
Friday, February 16, 2018: Heavy rains event prevented work as the river running at 80 CFS in the morning (35,907 GPM), and by the afternoon it was up to 200 CFS (89,767 GPM).
Main Road Bridge Replacement Update #5 - February 16, 2018
Friday, February 9, 2018: Roper Construction continued to haul off overburden to the Grindstone site to run through the grizzly and separate rock. The contractor is bringing a small excavator with Teledyne to complete rock removal at the north headwall, and George Esqueda from Zia Engineering was on-site doing inspections.
Main Road Bridge Replacement #3 - February 2, 2018
Crews completed the removal of both head walls and continued hauling off waste material as efforts continued to break-up larger pieces of concrete around the structure.
Main Road Bridge Construction Update #2 - January 26, 2018
Roper Construction began work on the Main Road Bridge on Monday, January 22, 2018, with the actual road closure occurring at 8:00 AM. The detour route began evolving with citizen and business owner input as the Village met with the NMDOT to take suggestions for the detour route.
Main Road Bridge Construction Coming - January 2018
The Main Road Bridge Project is set to kick-off in January 2018. There will be a lot of information coming out over the next few weeks about construction schedules, detour routes, and how to navigate the Upper Canyon during the project. Keep checking this page for updates.
Kick-off Meeting for Main Bridge No. 1 Project Scheduled
Upper Canyon residents are invited to attend a kick-off meeting about the Main Road No. 1 Bridge Project on February 28th at 1:00 PM at the Upper Canyon Fire Station. Project engineers and Village officials will be on-hand to answer questions.
Construction Begins on Cherokee Interconnect Project
The Village will begin work on the Cherokee Interconnect project today as it begins laying pipeline to connect the system to the Alto and Grindstone systems.